Alcoa Hwy: December 20, 2016
Charles Blalock & Sons, and their subcontractor Rogers Group is preparing to place asphalt base for the Maloney Road collector (roundabout). Once guardrail, asphalt pavement and pavement markings are installed, traffic will be turned onto the new section of roadway. This should allow for traffic to access Maloney Road and the adjacent properties without using the temporary runaround (see photo below).
Crews will be excavating for Wall #8 on the west side of Alcoa Hwy soon. In preparation for this work and subsequent fill activities on the opposite side of Alcoa near Mount Vernon, the contractor has excavated the grassy median section and placed stone fill. Trucks will be crossing Alcoa Hwy at this location (see below).