Alcoa Hwy: May 31, 2017
Contract CNQ029 Alcoa Highway SR 115 (US 129)
May 31, 2017 Project Update
Grading and fill operations are going well. Material from the large cut on the west side of Alcoa Hwy where Wall #8 is located is being hauled to the low area south of Montlake Dr. from Alcoa Hwy to Lynbrulee Ln. The photo below shows the haul road and benches in that cut. On the east side of Alcoa Hwy you can see the cut near Barber Hill Ln. Storm drain and utility relocations are also being installed and are on schedule.
Below you can see the view from Montlake Dr. looking south across the fill area where Ramp A will be constructed, connecting Montlake Dr. to Collector 3.