Alcoa Hwy: September 11, 2017
Contract CNQ029 Alcoa Highway SR 115 (US 129)
September 11, 2017 Project Update
The above photo is from the cut area above Wall #8. From this view you can see the cuts near Barber Hill and the fills at Mt. Vernon. Vegetation is starting to grow in these areas as well as above the wall. You can also see from this photo the crews working on the wall. At this time the wall is the critical activity of the project. Crews are continuing to work on other construction activities along the route as well, including storm drain installation and utility relocations. Crews will also start working on Collector Road #1 at Maloney Road beginning Monday, September 11, 2017. Motorist should expect to see detours to Ginn Dr.
Below are a close-ups of the Wall #8 construction.